Industrial Setup
A plant is permits, power, water and people before it is machines. The schedule is set by the slowest authorisation, not by construction.
Industrial projects in Morocco rarely fail on construction. They slip on an authorisation nobody put on the critical path, or on a grid connection assumed to be available.
The sequence that actually governs the timeline
- Site selection, which determines your regime, your incentives and your workforce pool.
- Land: purchase, long lease or allocation in an industrial zone, each with a different delay.
- Building permit, which depends on the applicable development plan.
- Environmental authorisation, which depends on the activity and can be the longest item.
- Grid connection and water allocation — to be requested early; capacity is not guaranteed by proximity.
- Operating authorisation specific to the activity.
- Workforce recruitment and certification, which takes longer than equipment installation for skilled roles.
Where projects lose months
Ordering equipment before the environmental authorisation is secured. Assuming the grid connection follows the building permit. Choosing a zone for its incentives without checking that it has the power capacity the process requires.
Regions
The right region depends on your inputs, your workforce and your route to market. Tangier for European logistics; Kenitra and Casablanca for automotive and aerospace supply chains; Agadir and Souss for agro-industry; the Oriental for cost and available land, with a thinner skilled labour pool.
What we do
We build the real critical path before you commit, obtain the authorisations in the order that governs it, and tell you when a site that looks attractive cannot deliver what your process needs.